Established in 2006 as a Community of Reality

Welcome to the Neno's Place!

Neno's Place Established in 2006 as a Community of Reality


Neno

I can be reached by phone or text 8am-7pm cst 972-768-9772 or, once joining the board I can be reached by a (PM) Private Message.

Join the forum, it's quick and easy

Established in 2006 as a Community of Reality

Welcome to the Neno's Place!

Neno's Place Established in 2006 as a Community of Reality


Neno

I can be reached by phone or text 8am-7pm cst 972-768-9772 or, once joining the board I can be reached by a (PM) Private Message.

Established in 2006 as a Community of Reality

Would you like to react to this message? Create an account in a few clicks or log in to continue.
Established in 2006 as a Community of Reality

Many Topics Including The Oldest Dinar Community. Copyright © 2006-2020


    The administration complains about the delay in ministerial projects.. Dhi Qar is reconstructing 77

    Rocky
    Rocky
    Admin Assist
    Admin Assist


    Posts : 281673
    Join date : 2012-12-21

    The administration complains about the delay in ministerial projects.. Dhi Qar is reconstructing 77  Empty The administration complains about the delay in ministerial projects.. Dhi Qar is reconstructing 77

    Post by Rocky Wed 17 Nov 2021, 6:25 am

    [size=52]The administration complains about the delay in ministerial projects.. Dhi Qar is reconstructing 77 sluggish school buildings out of 300[/size]

    [size=45]Dhi Qar / Hussein Al-Amil[/size]
    [size=45]The administration of Dhi Qar Governorate revealed a number of suspended and lagging ministerial projects in separate areas of the province, and while attributing the reasons for the reluctance to referring the ministerial projects to non-sober companies that are not subject to the supervision of the local administration in the province, it indicated that 77 school buildings have been reworked and the completion of three major ministerial projects During the past six months.[/size]
    [size=45]The problem of lagging ministerial and development projects in Dhi Qar governorate dates back to more than ten years, but it worsened further with the beginning of the financial crisis in 2014, when work stopped by about 440 service and development projects, which increased the suffering of the local population in the governorate, which has a population of more than two million people. .[/size]
    [size=45]The governor of Dhi Qar Ahmed Ghani al-Khafaji, whose government, formed seven months ago, inherited 183 lagging projects, "The lagging projects are divided into ministerial projects and others within the development plan of the province," and he explained that "the ministerial projects in the province, unfortunately, are all lagging, including the housing bridge project. The industrialist, who asked the ministry to withdraw the work and include the company on the blacklist, and the Olympic Stadium project, which we called on the Minister of Youth and Sports to find a solution to his problem.” Emphasizing the existence of complicated matters in the stadium file.[/size]
    [size=45]Al-Khafaji went on to talk to (Al-Mada), "There is also another ministerial project represented in the Shatrah sewer project, which is implemented by the Iranian Omar Ibb Company, which is sluggish and suspended, and we asked the General Secretariat of the Council of Ministers to intervene. And he added, “We will approach the Ministry of Municipalities again about finding appropriate solutions for the aforementioned project.”[/size]
    [size=45]And the governor of Dhi Qar continued, "In general, most of the ministries' projects are sluggish, and the companies that ministries contract with are often not solid and cause problems for the governorate, being the beneficiary of the services that the ministerial project is supposed to provide," noting that "the governorate's role is non-existent in selecting companies implementing ministerial projects." “.[/size]
    [size=45]Al-Khafaji revealed that "the local government and citizens are paying the price for the failure and delay of ministerial projects, some of which the ministries contracted for more than ten years."[/size]
    [size=45]The governor of Dhi Qar indicated that "the governorate administration, in its endeavors to address the file of lagging ministerial projects, was able to re-work a number of them during the past six months and to complete the completion stages of others, such as the Turkish hospital project, the highway bridge rehabilitation project, and the recently operated large reform water project."[/size]
    [size=45]Dhi Qar Governorate, which was classified by the Iraqi parliament in its numbered session (22) on December 18, 2019 as a stricken city, faces a severe shortage of basic services and the deterioration and aging of infrastructure, not to mention a severe shortage of clinical cover and a significant shortage of school buildings estimated at more than 700 buildings.[/size]
    [size=45]Regarding school building projects, Al-Khafaji said that “the file of school buildings in Dhi Qar governorate includes 305 school buildings, and in coordination with the General Secretariat of the Council of Ministers, we were able to re-work 77 of them,” noting that “work is underway to follow up on the aforementioned building projects.”[/size]
    [size=45]The governor of Dhi Qar pointed out that "the school building projects are distributed among various financing programs, including what is included in the financing of the Ministries of Education and Construction and Housing, and another section on the Chinese loan and other projects on the governorate development plan," adding that "each of these programs has its own problems."[/size]
    [size=45]Al-Khafaji revealed "special committees formed by the governorate administration to find solutions to the problems that hinder the implementation of the rest of the schools."[/size]
    [size=45]The Governor of Dhi Qar commended the role of the General Secretariat of the Council of Ministers in following up on the file of lagging projects, including school buildings, stressing, “The formation of a special committee in the General Secretariat to follow up on the mentioned projects and re-work in them, and that the committee and the governorate administration are working together in this field.”[/size]
    [size=45]The spokesman for the General Secretariat of the Council of Ministers, Haider Majid, had announced, on June 2, 2021, that the Secretary-General directed the companies executing the schools to intensify the effort and complete the buildings, otherwise the work will be withdrawn from the lagging companies and included in the blacklist. Revealing the re-working of 444 stalled and lagging projects across the country.[/size]
    [size=45]In turn, the assistant governor of Dhi Qar for Planning Affairs, Ghassan Hassan Al-Khafaji, said in previous media statements that “the local government continues to work to address the lagging projects it inherited and is serious about re-working on them,” adding that “there are 52 projects that have been re-announced because the estimated cost is for them.” It is less than what companies hope for, and it will have to adjust the cost.”[/size]
    [size=45]Hassan pointed out that "17 projects that have been withdrawn due to the delay, will be re-worked at the expense of the implementing companies."[/size]
    [size=45]The administration of Dhi Qar Governorate revealed on the ninth of this November, legal procedures to prosecute companies lagging behind in the implementation of a number of service projects, and while it confirmed sending final warnings to two companies implementing service projects at a cost of 164 billion dinars, it indicated that a high-ranking government delegation headed to Anbar Governorate for the purpose of review. On her experience in the field of reconstruction.[/size]